Sizing part buffers for unattended machine tending

A simple method to size drawer or tray buffers for the unattended run time you need.

00

Application Note

Sizing part buffers for unattended machine tending

A simple method to size drawer or tray buffers for the unattended run time you need.

Type

Application Note

Topic

Machine tending

Published

Mar 20, 2026

Access

Read online

The formula

Unattended time = parts in buffer per machine × cycle time per part.

Cycle time per part = machining time + robot load/unload time (when the machine waits for the robot).

Worked example

  • Machining time: 250 s

  • Robot load/unload: 38 s → cycle 288 s

  • Buffer: 140 blanks shared by 2 machines → 70 per machine

  • Unattended time: 70 × 288 s = 20,160 s = 5.6 h

Things that reduce real autonomy

  • Gauge-triggered stops when tolerances drift

  • Chip build-up on grippers or fixtures

  • Tool life shorter than the unattended period

  • Coolant level and chip conveyor capacity

Practical advice

Match tool life and chip capacity to the buffer before adding more buffer. A larger drawer system is of little use if a tool wears out after three hours.

Preparing a project?

Bring your requirements. An engineer will help shape the specification.

An engineer replies within one business day.

Preparing a project?

Bring your requirements. An engineer will help shape the specification.

An engineer replies within one business day.

Create a free website with Framer, the website builder loved by startups, designers and agencies.