Type
Checklist
Topic
Retrofit & modernization
Published
May 4, 2026
Access
Read online
Hardware and software
Inventory of every CPU, I/O module, drive and HMI, with firmware versions
Current program backups, verified to match what is running
Source code with comments, or confirmation that none exists
Licences for current engineering software
List of networked devices and addresses
Spare-parts stock and supplier status for each component
Documentation
Electrical drawings checked against the installed panel
Safety function list and most recent risk assessment
Interface list to upstream and downstream machines
Recipe and format data, with owner
Operations
Available shutdown windows for the next 12 months
Acceptable restart rate after cutover
Operators and technicians available for training
Known faults and workarounds collected from operators
Current downtime and MTTR baseline
Migration plan
Target platform agreed with maintenance and IT
Coding standard agreed
Simulation approach for logic testing
Panel pre-wiring and FAT plan
Cutover sequence with go/no-go points
Fallback plan if cutover fails
Safety reassessment scope
Documentation deliverables agreed
Support arrangement after go-live