FAT and SAT acceptance checklist

What to prepare, test and record at factory and site acceptance, so open items are visible rather than forgotten.

00

Checklist

FAT and SAT acceptance checklist

What to prepare, test and record at factory and site acceptance, so open items are visible rather than forgotten.

Type

Checklist

Topic

Commissioning

Published

Oct 22, 2025

Access

Read online

Before FAT

  • Test protocol agreed and signed before testing starts

  • Production parts or products available in the right quantity

  • Acceptance criteria stated as numbers, with measurement method

  • Client operators and maintenance staff invited

At FAT

  • Every safety function tested and recorded

  • Cycle time measured over a defined run, not a single cycle

  • Changeovers performed by client staff

  • Fault recovery tested for the most likely faults

  • Open items listed with owner and due date

Before SAT

  • Utilities, floor and interfaces confirmed on site

  • Installation plan aligned with production schedule

  • FAT open items closed or carried forward explicitly

At SAT

  • Safety functions re-tested in the final installation

  • Performance run under production conditions

  • Interfaces to upstream, downstream and MES verified

  • Documentation and backups handed over

  • Training completed and recorded

  • Remaining open items signed off with dates

  • Support contact and response terms confirmed

01

Related

Where this applies

01

Related

Where this applies

A

Solutions

B

Industries

C

More resources

Preparing a project?

Bring your requirements. An engineer will help shape the specification.

An engineer replies within one business day.

Preparing a project?

Bring your requirements. An engineer will help shape the specification.

An engineer replies within one business day.

Create a free website with Framer, the website builder loved by startups, designers and agencies.