Before FAT
Test protocol agreed and signed before testing starts
Production parts or products available in the right quantity
Acceptance criteria stated as numbers, with measurement method
Client operators and maintenance staff invited
At FAT
Every safety function tested and recorded
Cycle time measured over a defined run, not a single cycle
Changeovers performed by client staff
Fault recovery tested for the most likely faults
Open items listed with owner and due date
Before SAT
Utilities, floor and interfaces confirmed on site
Installation plan aligned with production schedule
FAT open items closed or carried forward explicitly
At SAT
Safety functions re-tested in the final installation
Performance run under production conditions
Interfaces to upstream, downstream and MES verified
Documentation and backups handed over
Training completed and recorded
Remaining open items signed off with dates