Project

PRJ-0264

Industry

Metals & Fabrication

Application

CNC machine tending

Commissioned

Mar 7, 2025

Status

Commissioned

Spindle utilisation raised from 54 % to 81 % by running both lathes through an unmanned night period.

Project

PRJ-0264

Industry

Metals & Fabrication

Application

CNC machine tending

Commissioned

Mar 7, 2025

Status

Commissioned

Spindle utilisation raised from 54 % to 81 % by running both lathes through an unmanned night period.

Plan drawing of the two-lathe tending cell

FIG. 1

CNC machine tending

PRJ-0264

01

Commissioning results

Measured outcome

01

Commissioning results

Measured outcome

Spindle utilisation

54

→

81

%

Average of 2 lathes · 8 weeks after SAT vs. 8 weeks before

Spindle utilisation

54

→

81

%

Average of 2 lathes · 8 weeks after SAT vs. 8 weeks before

Weekly output

+50

%

Same part family and machining time · ratio 81 ÷ 54

Weekly output

+50

%

Same part family and machining time · ratio 81 ÷ 54

Load / unload time

75

→

38

s

Per part · manual vs. robot

Load / unload time

75

→

38

s

Per part · manual vs. robot

Unattended autonomy

5.6

h

140 blanks ÷ 2 lathes × 288 s cycle

Unattended autonomy

5.6

h

140 blanks ÷ 2 lathes × 288 s cycle

02

Engineering record

Challenge, approach and architecture

02

Engineering record

Challenge, approach and architecture

Challenge

Context. Two CNC lathes machining steel hydraulic fittings, 4–12 kg blanks, in batches of 200 to 2,000.

Existing process. One operator loaded both machines on two shifts. Machining time was 250 s per part, but loading took 75 s and the second machine often waited while the first was loaded, measured, or the operator was elsewhere. Neither machine ran at night.

Constraints.

  • Parts up to 12 kg, oily, with sharp edges.

  • Batch changes two to three times per week.

  • Machine builder approval for door, chuck and coolant interfaces.

Challenge

Context. Two CNC lathes machining steel hydraulic fittings, 4–12 kg blanks, in batches of 200 to 2,000.

Existing process. One operator loaded both machines on two shifts. Machining time was 250 s per part, but loading took 75 s and the second machine often waited while the first was loaded, measured, or the operator was elsewhere. Neither machine ran at night.

Constraints.

  • Parts up to 12 kg, oily, with sharp edges.

  • Batch changes two to three times per week.

  • Machine builder approval for door, chuck and coolant interfaces.

Engineering approach

One robot on a fixed base between the two lathes, a drawer buffer for blanks and finished parts, and an in-cell gauge so the cell stops if a diameter drifts toward its limit.

Scope. Cell layout and reach study; FANUC robot, 25 kg payload, 1,800 mm reach; dual grippers with quick-change jaws per part family; 7-drawer buffer with 20 positions per drawer; gauge station; safety fencing with an operator loading window; cell PLC and HMI for batch changeover.

Engineering approach

One robot on a fixed base between the two lathes, a drawer buffer for blanks and finished parts, and an in-cell gauge so the cell stops if a diameter drifts toward its limit.

Scope. Cell layout and reach study; FANUC robot, 25 kg payload, 1,800 mm reach; dual grippers with quick-change jaws per part family; 7-drawer buffer with 20 positions per drawer; gauge station; safety fencing with an operator loading window; cell PLC and HMI for batch changeover.

System architecture

  • Robot: 25 kg payload, 1,800 mm reach, dual gripper (raw / finished part).

  • Buffer: 7 drawers × 20 positions = 140 blanks.

  • Machine interface: door, chuck and cycle-start signals via the CNC builder's automation interface.

  • Gauging: in-cell diameter gauge, results logged per part; cell stops on trend toward limit.

  • Safety: fenced cell, safety laser scanner at the drawer loading window.

System architecture

  • Robot: 25 kg payload, 1,800 mm reach, dual gripper (raw / finished part).

  • Buffer: 7 drawers × 20 positions = 140 blanks.

  • Machine interface: door, chuck and cycle-start signals via the CNC builder's automation interface.

  • Gauging: in-cell diameter gauge, results logged per part; cell stops on trend toward limit.

  • Safety: fenced cell, safety laser scanner at the drawer loading window.

Deployment & commissioning

Each lathe was offline for two days during installation, one after the other. Gripper jaws for five part variants were tested at FAT; three more were added during the first month.

Open item at SAT: batch changeover averaged 26 minutes against a 20-minute target. Jaw changes are within time; drawer re-teaching is not. A drawer template per part family is being added.

Deployment & commissioning

Each lathe was offline for two days during installation, one after the other. Gripper jaws for five part variants were tested at FAT; three more were added during the first month.

Open item at SAT: batch changeover averaged 26 minutes against a 20-minute target. Jaw changes are within time; drawer re-teaching is not. A drawer template per part family is being added.

  1. BUFDrawer buffer140 blanks
  2. ROBLoadDual gripper
  3. CNCMachine250 s per part
  4. GAUGEMeasureDiameter per part
  5. OUTUnloadOK / NOK drawer
FIG. 3 · Signal path · Rev A

03

Specification & results

Specification, acceptance and results

03

Specification & results

Specification, acceptance and results

Robot payload

Part 12 kg + dual gripper

25 kg

Robot payload

Part 12 kg + dual gripper

25 kg

Reach

1,800 mm

Reach

1,800 mm

Buffer

Drawer system

7 × 20 = 140 blanks

Buffer

Drawer system

7 × 20 = 140 blanks

Machining time

Per part, unchanged

250 s

Machining time

Per part, unchanged

250 s

Part weight

Steel hydraulic fittings

4–12 kg

Part weight

Steel hydraulic fittings

4–12 kg

Parameter

Specified

Measured

Result

Load / unload time

≤ 45 s

38 s

Pass

Load / unload time

Specified

≤ 45 s

Measured

38 s

Result

Pass

Gauge repeatability

≤ 4 µm

2.6 µm

Pass

Gauge repeatability

Specified

≤ 4 µm

Measured

2.6 µm

Result

Pass

Unattended run

≥ 5 h

5.6 h

Pass

Unattended run

Specified

≥ 5 h

Measured

5.6 h

Result

Pass

Batch changeover

≤ 20 min

26 min

Open item

Batch changeover

Specified

≤ 20 min

Measured

26 min

Result

Open item

Results

Measure

Before

After

Machines per operator

2, constantly attended

2, attended for loading and changeover only

Night shift

Not run

5.6 h unattended

Load / unload

75 s

38 s

Spindle utilisation

54 %

81 %

The cycle per part is 288 s (250 s machining + 38 s load/unload). With 70 blanks per lathe, the cell runs 5.6 h without an operator.

Results

Measure

Before

After

Machines per operator

2, constantly attended

2, attended for loading and changeover only

Night shift

Not run

5.6 h unattended

Load / unload

75 s

38 s

Spindle utilisation

54 %

81 %

The cycle per part is 288 s (250 s machining + 38 s load/unload). With 70 blanks per lathe, the cell runs 5.6 h without an operator.

04

Drawings

Layout and detail drawings

Original technical drawings prepared for this record. Illustrative, not to scale.

04

Drawings

Layout and detail drawings

Original technical drawings prepared for this record. Illustrative, not to scale.

Plan drawing of the two-lathe tending cell

FIG. 1 · Machine-tending cell, plan view

Buffer autonomy calculation drawing

FIG. 2 · Buffer autonomy: 70 blanks × 288 s = 5.6 h

The machines now run at night, and in the morning there is a drawer of measured parts instead of an idle shop.

Production Manager

Client · precision machining (anonymized)

PRJ-0264

Have a similar application?

Discuss a machine-tending cell

An engineer replies within one business day.

Have a similar application?

Discuss a machine-tending cell

An engineer replies within one business day.

Create a free website with Framer, the website builder loved by startups, designers and agencies.